ravb-odoo 29caafdf93 [FIX] project: fix allocate hour of sub-tasks issue
Description of the issue/feature this PR addresses:
in project task form, allocated time of parent task. The 'incl. x on sub-tasks'
field is taking allocated time of all the child task as well as sub-tasks of its
child task. Field should only take into account time allocated to the first
level of sub-tasks.

Current behavior before PR:
field shows allocated hours of child task as well as sub-task of child-tasks.

Desired behavior after PR is merged:
field shows allocated hours of only child-tasks.

Fix:
removed child_task.subtask_planned_hour from the compute method of
subtask_planned_hour fields so that its only add the hours of its child-tasks
and not its sub-task of child-tasks.

task-3277977

closes odoo/odoo#140989

X-original-commit: f42cfb351a86f8ec551066d71271b97a56ce92b4
Signed-off-by: Xavier Bol (xbo) <xbo@odoo.com>
2023-11-06 11:16:44 +00:00
..
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-25 19:37:35 +00:00
2023-10-26 08:45:57 +00:00
2023-10-25 18:11:01 +00:00
2023-10-10 17:26:34 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00
2023-11-02 21:02:44 +00:00
2023-10-27 08:36:16 +00:00
2023-10-27 08:36:16 +00:00