[FIX] mrp: real duration
- Create a MO which generates WOs - User 1 starts working on it - User 2 starts working on it The field 'Real Duration' only displays the time spent by the user connected. It means that there will be an inconsistency between the field 'Real Duration' and the list of durations shown in the `time_ids` field. We want to keep 'Real Duration' limited to the current user, because it should represent the duration updated in real time (done in widget `mrp_time_counter`). However, we also want to see the total real drations for all users. Thereofe, we simply update the view to show the total in the list view. opw-784456
This commit is contained in:
committed by
Nicolas Martinelli
parent
fdf0f014bf
commit
e5f61fa10c
@@ -201,7 +201,7 @@
|
||||
<tree>
|
||||
<field name="date_start"/>
|
||||
<field name="date_end"/>
|
||||
<field name="duration" widget="float_time"/>
|
||||
<field name="duration" widget="float_time" sum="Total duration"/>
|
||||
<field name="user_id"/>
|
||||
<field name="loss_id" string="Efficiency"/>
|
||||
</tree>
|
||||
@@ -459,4 +459,4 @@
|
||||
<field name="view_id" ref="view_work_center_load_graph"/>
|
||||
<field name="act_window_id" ref="action_mrp_workcenter_load_report_graph"/>
|
||||
</record>
|
||||
</odoo>
|
||||
</odoo>
|
||||
|
||||
Reference in New Issue
Block a user