[IMP] mrp: help message for the explaining the Next Operation field on the routing

This commit is contained in:
Josse Colpaert
2016-09-28 12:38:13 +02:00
parent 219809a5a8
commit 3e95e4e58e
+1
View File
@@ -69,6 +69,7 @@ class MrpRoutingWorkcenter(models.Model):
batch = fields.Selection([
('no', 'Once all products are processed'),
('yes', 'Once a minimum number of products is processed')], string='Next Operation',
help="""Will determine if the next work order will be planned after the previous one or after the first Quantity To Process of the previous one.""",
default='no', required=True)
batch_size = fields.Float('Quantity to Process', default=1.0)
workorder_ids = fields.One2many('mrp.workorder', 'operation_id', string="Work Orders")