[IMP] added task_process.yml for task sheduling in project_long_term module
bzr revid: tpa@tinyerp.com-20111213052012-6eo11iszu07yo0mt
This commit is contained in:
@@ -44,6 +44,7 @@ Features
|
||||
"demo_xml": ["project_long_term_demo.xml"],
|
||||
"test": [
|
||||
'test/phase_process.yml',
|
||||
'test/task_process.yml',
|
||||
],
|
||||
"update_xml": [
|
||||
"security/ir.model.access.csv",
|
||||
|
||||
@@ -0,0 +1,20 @@
|
||||
-
|
||||
I create a record to compute the tasks of project.
|
||||
-
|
||||
!record {model: project.compute.tasks, id: project_compute_tasks0}:
|
||||
project_id: project.project_integrate_openerp
|
||||
-
|
||||
I compute and shedule the tasks.
|
||||
-
|
||||
!python {model: project.compute.tasks}: |
|
||||
self.compute_date(cr, uid, [ref("project_compute_tasks0")])
|
||||
-
|
||||
Check if tasks scheduled, check that either of task's start_date, end_date and user_id is not null
|
||||
-
|
||||
!python {model: project.project}: |
|
||||
prj = self.browse(cr, uid, [ref("project.project_integrate_openerp")])[0]
|
||||
for task in prj.tasks:
|
||||
if task.state in ('done','cancelled'):
|
||||
continue
|
||||
if (not task.user_id) or (not task.date_start) or (not task.date_end):
|
||||
raise AssertionError("Project tasks not scheduled!")
|
||||
Reference in New Issue