cancelling propagation in a move chain was True be default. That means,
without any configuration, a cancel move will always cancel its next ones
This commit change the default to allow only cancelation of move chain
until the stock location. Here are 2 examples :
1. Reception and delivery in 3 steps. The moves chain is the following:
Vendor -> Input -> Quality -> Stock -> Pack -> Output -> Customer
In case the Purchase order is cancelled, we want to move from Vendor to
Stock are cancelled but not the ones from Stock.
2. pbm + sam. The manufacturing process is the following;
Stock -> Pre-prod -> Production -> Post-prod -> Stock
cancelling the first move should cancelled until Production and not after
Task : 1913297