Nicolas Martinelli 92aeaa47ff [FIX] mrp: date expected and date deadline
- Create Product A:
  Routes: MTO and Manufacture
  Manufacturing Lead Time: 20 days
- Create Product B:
  Routes: MTO and Buy
  Add a supplier with Delivery Lead Time: 10 days
- Create a BOM: 1 unit of B to produce 1 unit of A
- Create a SO for A, validate

A MO is created with a Deadline set at SO order date - 20 days => OK
A PO is created with order date set at SO order date - 10 days => Not
OK, it should be - 30 days.

In v13, the raw materials expected date is the order date.
In v12, this date is computed as: order date minus Manufacturing Lead
Time

However, in both versions the PO order date is computed as the raw
materials expected date minus Delivery Lead Time of the supplier.

This comes from a change in the semantic of 'Planned Date' and 'Planned
End Date'. In v13, the Manufacturing Lead Time is only taken into
account in the Deadline, while in v12 it was taken into account in the
Planned Date. However, the expected date of the raw materials still
relies on the latter, not on the Deadline.

In order to solve this, we apply the 'Manufacturing Lead Time' of the
product and the company to 'Planned Date', 'Planned End Date' and
'Deadline' when the MO is created. Note that the solution is still not
ideal in case no routing is set on the BOM since 'Planned Date' and
'Planned End Date' won't be updated later in the process.

opw-2118951

closes odoo/odoo#40360

X-original-commit: b523f991572e32e69c5f8000a21553191ca54773
Signed-off-by: Nicolas Martinelli (nim) <nim@odoo.com>
2019-11-15 15:21:51 +00:00
..
2019-09-03 15:05:03 +00:00
…
2019-10-21 12:12:48 +00:00
2019-10-24 09:34:11 +00:00
2019-09-13 14:30:50 +00:00
2019-11-13 11:05:14 +00:00
…

Odoo Manufacturing Resource Planning

Manage Bill of Materials, plan manufacturing orders, track work orders with the Odoo Open Source MRP app.

Get all your assembly or manufacturing operations managed by Odoo. Schedule manufacturing orders and work orders automatically. Review the proposed planning with the smart kanban and gantt views. Use the advanced analytics features to detect bottleneck in resources capacities and inventory locations.

Schedule Manufacturing Orders Efficiently

Get manufacturing orders and work orders scheduled automatically based on your procurement rules, quantities forecasted and dependent demand (demand for this part based on another part consuming it).

Define Flexible Master Data

Get the flexibility to create multi-level bill of materials, optional routing, version changes and phantom bill of materials. You can use BoM for kits or for manufacturing orders.

Get Flexibility In All Operations

Edit manually all proposed operations at any level of the progress. With Odoo, you will not be frustrated by a rigid system.

Schedule Work Orders

Check resources capacities and fix bottlenecks. Define routings and plan the working time and capacity of your resources. Quickly identify resource requirements and bottlenecks to ensure your production meets your delivery schedule dates.

A Productive User Interface

Organize manufacturing orders and work orders the way you like it. Process next orders from the list view, control in the calendar view and edit the proposed schedule in the Gantt view.

Inventory & Manufacturing Analytics

Track the evolution of the stock value, according to the level of manufacturing activities as they progress in the transformation process.

Fully Integrated with Operations

Get your manufacturing resource planning accurate with it's full integration with sales and purchases apps. The accounting integration allows real time accounting valuation and deeper reporting on costs and revenues on your manufacturing operations.