Fabien Pinckaers 0d2ae40a70 [FIX] Complete refactoring of project_long_term, with following changes:
do not use resources but users on phases:
     - to be consistent with project members and task responsible
     - if the user is linked to a resource, it uses the calendar of the resource (holidays for example)
  better YML tests
  Complete rewrite of the scheduling mechanism:
    - Schedule phases:
        - write project.user.allocation based on scheduling
        - schedule resources based on members on the project
        - new constraint: force some users on a phase
    - Schedule tasks:
        - set user if no user on task
        - set start and end date
  some useability improvements

We still have to work on better Gantt view but I think the scheduling is
working correctly now.

bzr revid: fp@tinyerp.com-20111025233141-cgctwe8spxhko2gn
2011-10-26 01:31:41 +02:00

119 lines
4.4 KiB
YAML

-
Given that I have a project 'Test Phases'.
-
!record {model: project.project, id: project_project_developyamlproject0}:
name: "Develop Yaml Project Module"
date_start: !eval time.strftime('%Y-%m-%d')
resource_calendar_id: resource.timesheet_group1
members:
- base.user_admin
-
And I create three human ressources to work on this project, an analyst.
-
!record {model: resource.resource, id: resource_resource_analyst1}:
calendar_id: resource.timesheet_group1
name: Analyst
resource_type: user
time_efficiency: 1.0
user_id: base.user_admin
-
I define a developer HR.
-
!record {model: resource.resource, id: resource_resource_develop0}:
calendar_id: resource.timesheet_group1
name: Developer
resource_type: user
time_efficiency: 1.0
user_id: base.user_admin
-
I define a tester HR.
-
!record {model: resource.resource, id: resource_resource_tester1}:
calendar_id: resource.timesheet_group1
name: tester
resource_type: user
time_efficiency: 1.0
user_id: base.user_admin
-
Then I create three phases for my projects; Analysis, Development, Testing.
-
The first phase is 'Analysis' and has a duration of 6 days.
-
!record {model: project.phase, id: project_phase_analysisflowforyaml0}:
date_start: !eval time.strftime('%Y-%m-%d')
duration: 6.0
name: "Analysis"
product_uom: product.uom_day
project_id: project_project_developyamlproject0
state: draft
-
I update the constrain and the analysis phase to not start before 4 days.
-
!python {model : project.phase }: |
pass
import datetime
from dateutil.relativedelta import *
start = datetime.date.today() + relativedelta(days=4)
self.write(cr,uid, [(ref("project_phase_analysisflowforyaml0"))], {'constraint_date_start': start})
-
The second phase is 'Development' and depend on the 'Analysis', with a duration of 6 days.
-
!record {model: project.phase, id: project_phase_developyaml0}:
duration: 6.0
name: Development
product_uom: product.uom_day
project_id: project_project_developyamlproject0
previous_phase_ids:
- project_phase_analysisflowforyaml0
-
I update the Constrain Date Start adn Date End for phase Develop yaml
-
!python {model : project.phase }: |
pass
import datetime
#from dateutil.relativedelta import *
#start = datetime.date.today() - relativedelta(days=5)
#end = datetime.date.today() + relativedelta(days=10)
#self.write(cr,uid, [(ref("project_phase_developyaml0"))], {'constraint_date_start': start, 'constraint_date_end':end})
-
The third phase is 'Testing' and depend on the 'Develop' phase, with a duration of 6 days.
-
!record {model: project.phase, id: project_phase_testyaml0}:
duration: 6.0
name: Testing
product_uom: product.uom_day
project_id: project_project_developyamlproject0
previous_phase_ids:
- project_phase_developyaml0
-
Then I launch the scheduler to compute starting and ending phases on all phases of this project.
-
!record {model: project.compute.phases, id: project_compute_phases_0}:
project_id: project_project_developyamlproject0
target_project: one
-
!python {model: project.project}: |
self.schedule_phases(cr, uid, [ref("project_project_developyamlproject0")])
-
After scheduling, I check the starting date and ending date on the phases are correct.
-
!python {model: project.phase}: |
import datetime
from dateutil.relativedelta import *
minstart = (datetime.date.today() + relativedelta(days=4)).strftime('%Y-%m-%d')
minend = (datetime.date.today() + relativedelta(days=11)).strftime('%Y-%m-%d')
phase1=self.browse(cr, uid, ref('project_phase_analysisflowforyaml0'))
assert phase1.date_start>=minstart, 'Error, the Analysis phase '+phase1.date_start+' should start after '+str(minstart)
assert phase1.date_end>=minend, 'Error, the Analysis phase should end after '+str(minend)
phase2=self.browse(cr, uid, ref('project_phase_developyaml0'))
assert phase2.date_start>=phase1.date_end, 'Error, the phase Development should start after the end of the Analysis phase'
phase3=self.browse(cr, uid, ref('project_phase_testyaml0'))
assert phase3.date_start>=phase2.date_end, 'Error, the phase Testing should start after the end of the Development phase'
assert phase3.date_start<phase3.date_end, 'Error, the phase Testing should start before ending'