JF Aubert dbd09f16a2 [IMP] mrp,mrp_workorder: workorder scheduling revamp
Currently MRP only allows sequential scheduling of work orders.

This commit allows to specify the dependencies for work orders to be
scheduled in parallel or in a complex diagram.

By enabling the feature in the settings and at the bom level,
you can specify dependencies between operations:
on the operation form, select the operations on which the
current one depends.

The dependencies will be reflected in work orders during planning.

The workorders Gantt view has been adapted for you to visualize
and manipulate the dependencies.

Please note:
- work orders without predecessors will be started first
- they can all be done in parallel
- when all work orders of this step are finished, their successors
  will start
- and so on, step by step

Also, with the feature activated at the bom level and no dependency,
the parallel scheme will be applied (all operations at first step).

Finally, without activation at the bom level, the dependencies will
be created in order to satisfy the current sequential model.

Task: 2691328
Part-of: odoo/odoo#87131
2022-06-03 16:40:08 +02:00
..