Nicolas Martinelli 01c567c376 [FIX] mrp: Time Cycle computation
- Create a workcenter with a capacity of 500 units
- Create a BOM with a routing generating one work order in the WC
  created
- Create 3 MO with the following real durations:
  MO 1: 1000 units produced in 420.95 seconds
  MO 2: 1000 units produced in 120.28 seconds
  MO 3: 1000 units produced in 60 seconds
- Create a MO for 1 unit

The Duration expected is computed as

The Time Cycle is computed as:
  (420.95 + 120.28 + 60) / (1000 + 1000 + 1000) = 0.20041
The Total Expected is computed as:
  0 + 0 + (1.0 * 0.20041) * (100.0 / 100.0) = 0.20041

0.20041 seconds is not realistic based on the previous MO real
durations.

This is because the Time Cycle doesn't take into account the workcenter
capacity. If we can produce 60 units in parallel in 60 seconds, that
doesn't mean we can produce 1 unit in 1 second. Therefore, the Time
Cycle should be multiplied by the WC capacity, which gives a Time Cycle:

   500 * (420.95 + 120.28 + 60) / (3000) = 100.205

Which is much closer to the real duration.

opw-2070759

closes odoo/odoo#37548

X-original-commit: 9d3a73f64feb3b9e71c50a04adb6206b6393c757
Signed-off-by: Nicolas Martinelli (nim) <nim@odoo.com>
2019-09-27 17:51:21 +00:00
..
2019-09-03 15:05:03 +00:00
2019-09-03 15:05:03 +00:00
2019-09-03 15:05:03 +00:00
2019-08-20 12:43:59 +00:00
2019-09-03 15:05:03 +00:00
2019-09-03 15:05:03 +00:00