Case 1: To check order date of purchase order and schedule dates of shipment and purchse order,
- Configure lead times:
- At a product level set Delivery Lead Time
- At a company level set Purchase Lead Time
Case 2: To check order date of purchase order and schedule dates of multiple purchase order line of the same purchase order,
we create two procurements for the two different product with same vendor and different Delivery Lead Time
Case 3: To check order date of purchase order and schedule dates of shipments and purchase order,
- Configure lead times:
- At a product level set Delivery Lead Time
- At a route level set delay of push rules
Detailed Use Cases
==================
Consider today's date = 2016-04-21 ( date_planned of procurement = today's date + 10 days)
CASE 01:
========
Create Product
--------------
Name : Product A
Product type : stockable
Buy : True
Make To Order : True
Delivery Lead Time : 5 days
Configure your company data
---------------------------
Purchase Lead Time : 3.00 days
Procurement Request
-------------------
Warehouse : YourCompany
Product : Product A
Quantity : 15.00
Planned Date: 2016-05-01 00:00:00
Confirm Purchase Order
Result
------
Purchase Order :-- Schedule date: 2016-04-28 00:00:00
Order date: 2016-04-23 00:00:00
Incoming shipments schedule date :-- 2016-04-28 00:00:00
CASE 02:
========
Create Product
--------------
Name : Product A
Product type : stockable
Buy : True
Make To Order : True
Delivery Lead Time : 5 days
Create another Product
----------------------
Name : Product B
Product type : stockable
Buy : True
Make To Order : True
Delivery Lead Time : 2 days
Procurement Request
-------------------
Warehouse : YourCompany
Product : Product A
Quantity : 10.00
Planned Date: 2016-05-01 00:00:00
Procurement Request for second product
--------------------------------------
Warehouse : YourCompany
Product : Product B
Quantity : 5.00
Planned Date: 2016-05-01 00:00:00
Confirm Purchase Order
Result
------
Purchase Order :-- Schedule date: 2016-04-28 00:00:00
Order date: 2016-04-26 00:00:00
Schedule date of purchase order line for product A: 2016-05-01 00:00:00
Schedule date of purchase order line for product B: 2016-04-28 00:00:00
Incoming shipments schedule date :-- 2016-04-28 00:00:00
CASE 03:
========
Create Product
--------------
Name : Product A
Product type : stockable
Buy : True
Make To Order : True
Delivery Lead Time : 5 days
Warehouse configuration (YourCompany)
-------------------------------------
Incoming shipments : three steps
Routes
------
YourCompany : Receipt in 3 steps
Push Rules:
-----------------
WH: Input -> Quality Control :-- Delay : 2 days
WH: Quality Control -> Stock :-- Delay : 2 days
Create Procurement:
-------------------
Product : Prosuct A
Quantity : 5.000
Warehouse : YourCompany
Procurement Location : WH/Input
Schedule date : 2016-05-01 10:30:43
Notes : 'Test scheduler for RFQ'
Confirm Purchase Order
Result
------
Purchase Order :-- Schedule date: 2016-05-01 10:30:43
Order date: 2016-04-26 10:30:43
Incoming shipments schedule dates :--
In type :-- 2016-05-01 10:30:43
Internal type 1 :-- 2016-05-03 10:30:43
Internal type 2 :-- 2016-05-05 10:30:43