Add a operation type (`stock.picking.type`) for
the subcontracting resupply in order to distinct
easily the a simple delivery and a resupply to a subcontractor.
task-2486811
Part-of: odoo/odoo#75041
Steps to reproduce the bug:
- Let's consider a consumable product P with a subcontracted BOM B
- Let's consider that B is subcontracted by a partner S and B has a storable component C
- C has the route Resupply Subcontractor on Order and has a partner SUP as supplier
- Create a purchase order PO with 1 P to S and confirm PO
- A delivery order DO1 is created with C to S
- Change the ordered quantity on PO and set 2 instead of 1
Bug:
DO1 was canceled and a new delivery order DO2 was created with only 1 C instead of 2
It happens due to merge move, when updating the PO line a new rule is
trigger and create the object in this order:
- Move Sub-Stock(finished) -> Subcontract Order -> Move Stock-Sub(comp)
Then the action_confirm is trigger and will run _merge_move
on object from left to right order. But when the move Sub-Stock is
merged, everything is write in the first move and the new move is
unlink. It result by canceling all the following object (so the new
subcontractor and the Move Stock-Sub). It was not an issue for the
subcontracting since the write of stock.move is overridden in order
to update the order quantity when the move quantity is updated.
However in this case the rule are not triggered in order to create
the moves that ressuply the subcontractor.
In order to avoid this mess, this PR prevent the merge in case of a
subcontracting move.
opw-2419222
closesodoo/odoo#69553
X-original-commit: c6447e724b9df3c25c5a5306fc902dfc5dcd6bb8
Signed-off-by: Arnold Moyaux <amoyaux@users.noreply.github.com>
Co-authored-by: simongoffin <sig@odoo.com>
Improve onboarding by removing the replenish on order route.
Companies that do MTO process could unarchive the route in
order to have a basic configuration.
closesodoo/odoo#55147
Task: 2245882
Signed-off-by: Arnold Moyaux <amoyaux@users.noreply.github.com>
Allow to do a dropshipping with a subcontractor.
If the product uses the routes drophipping and have
a subcontracting BoM. Then a PO for the subcontractors
will genrate a need in the subcontracting location for
the required components.
A module is needed because the picking_type_id for dropshipping
do not have a warehouse_id. The warehouse_id is needed in order to
know from which warehouse the subcontracting components should be
deliver.