Josse Colpaert c2040da0ba [REF] mrp: inventory post when last work order is finished
Before this patch, the inventory was automatically posted when you click
on "done" on the last planned work order. This behavior was preventing
the user from correcting, for example, the consumed quantity on the raw
materials move on the manufacturing order if it was different from the
theoretical quantity. Note that finishing anyone but the last work order
still let you edit the consumed quantity. Same with changing the lot.

Now you have to click on "mark as done" on the manufacturing order to
post the inventory. Note that this is the same behavior when working
without work order (produce > mark as done will post).

We adapt the tests to reflect this change.
2017-01-10 15:32:14 +01:00
Thibault Delavallée c8a313d51e [IMP] various: use odoo for imports instead of openerp and update class names 2016-08-10 15:48:07 +02:00
Thibault Delavallée 53fe7e9fa6 [TESTS] mrp and various: updating tests 2016-07-04 16:22:37 +02:00
Josse Colpaert 2ddc35a530 [REF][NEWPIE] mrp: new MRP
This commit contains the core of the new MRP. It contains a whole refactoring
of the MRP application, with improved and new features, written in new API.
Among other here are the main manufacturing workflow improvements :

 - Picking type not only for pickings but also for manufacturing orders
 - Properties replaced by picking type
 - BoM can only be produced with its routing (no other)
 - Either produce without routing with only production orders, or produce with
   routing
 - By default, there is an order in the work orders (serially), but you can
   override it to be able to work in parallel
 - Time clocking on work orders and block time on work centers with reporting
   on OEE, performance, losses, ...
 - Real-time adaptation of timings on operations
 - Lots/serial numbers can be inputted like in the pickings on manufacturing
   orders.  It is also possible to input them in the work orders.
 - Material availability independent of production order state (possibility to
   start production when only part of it is there)
 - Work sheets on work orders
 - Put messages on work orders to make your workers pay attention to something
 - Full traceability link to see for each produced piece of stock, the
   consumed pieces, ...
 - Separate scrap object (a scrap is not done based on an original move
   anymore)
 - Separate unbuild system (if you want to unbuild into its original
   components)

Thanks to all people that helped during this development, notably but not
limited to Chirag A Dodiya (cod@odoo.com), Gaurav Panchal (gan@odoo.com),
Jignesh Rathod (jir@odoo.com), Mansi Trivedi (mtr@odoo.com), Pariket Trivedi
(ptr@odoo.com).