We would like to be able to take leaves using different units, currently
we only support taking leaves by hours because we use datetimes.
We need to support three units:
* days
* half days
* hours
These units will be defined on the leave type.
Task #40995Closes#21760
Using a working calendar, you might want to know
how much hour correspond a work day. This depends
of you working calendar. This might be usefull to
compute leave duration (half a day is not 8 hours,
but 4).
The hours_per_day field is not computed as the
average of working hour of all work day of calendar
to allow customization. By default, it is 8, as
the default attendances are the one from the
40h/week calendar.
A constant is also available to handle case where
resource calendar is not available.
Since some calendar are in data, and their attendances
in an 'eval' with '0' ORM command, we need to put them
in noupdate mode to avoid duplicating attendances when
we update the module.
This commit proposes to add 35 and 38 hours/week resource calendars.
Those are considered as standard for a lot of countries. This helps
users starting with odoo time tracking.
Purpose of this commit is to always have a default calendar for each
company and ensure it is correctly set on resources.
Some cleaning is also performed in resource models to remove unused
fields, improve labels and make views a bit more odoo-ish.
* [REF] res_company: add a m2o to the default calendar to use in the
company as well as a o2m linking all resource calendars used in the
company. Some code has been added to correctly update existing
companies when installing the module;
* [REF] resource_calendar
* [REM] manager field on resource.calendar: this field is never used
and is not necessary anyway
* [ADD] global_leave_ids: filter leaves on a calendar to see global
company leaves
* [IMP] better default company / calendar computation to ensure there
is always a calendar attached to a resource
* [IMP] improve resource and calendar views in order to look more like
other odoo views
Currently there is no default resource calendar. This leads to calendar
being rarely used as it is not clear how to define them and how to use
them. Moreover some code handle default-like calendar by trying to
use 8-16 work hours; this should be replaced by having a real default
calendar.
This commit replaces the demo calendar by a real data calendar. It will
soon be used as default everywhere a resource calendar can be defined.
Future improvements will come to make resource easier to use and clean
its API. This commit is only the beginning !