[FIX] procurement: magic bypass transition was incomplete and preventing pulled flows from working
The procurement workflow has a magic `bypass` transition that acts as a fallback for MTO procurements in case the necessary modules are not (yet) installed. For example it will consider a MTO+Buy procurement directly satisfied if the Purchase module is not yet installed. However this bypass transition did not properly take "internal pulled flows" into account, which are added by the `stock_location` module as a third kind of procurement type. In this case the bypass would match and never give stock_location the chance to run. In order to be consistent with the other procurement methods, the bypass transition needs to be adapted. Also updated the check_move() method to make it more explicit rather than a side-effect. bzr revid: odo@openerp.com-20131112151747-da67h4yavhz3k29c
This commit is contained in:
@@ -147,9 +147,11 @@
|
||||
|
||||
<record id="trans_confirm_mto_make_done" model="workflow.transition">
|
||||
<!-- This transition is there to unblock products that would be in MTO with a supply method that would be
|
||||
produce or buy without MRP or purchase module installed. These modules overwrite the check_produce()
|
||||
produce or buy, and without MRP or Purchase modules installed. These modules overwrite the check_produce()
|
||||
and check_buy() methods -so that it invalidates their part of this 'bypass transition'-, and define
|
||||
their own workflow paths.
|
||||
The stock_location module also introduces a check_move() alternative, for pulled flows that are
|
||||
satisfied with an internal product move. This yields a threefold test for the bypass transition.
|
||||
-->
|
||||
<field name="act_from" ref="act_confirm_mto"/>
|
||||
<field name="act_to" ref="act_make_done"/>
|
||||
|
||||