[FIX] project_long_term: remove onchange day on project.phase module. no need to change end date of phase. we can schedule end date using scheduler phase
bzr revid: hmo@tinyerp.com-20101230105727-ev1fppejij0ngv32
This commit is contained in:
@@ -144,13 +144,6 @@ class project_phase(osv.osv):
|
||||
result['date_start'] = project_id.date_start
|
||||
return {'value': result}
|
||||
|
||||
def onchange_days(self, cr, uid, ids, project, context=None):
|
||||
result = {}
|
||||
for id in ids:
|
||||
project_id = self.browse(cr, uid, id, context=context)
|
||||
newdate = datetime.strptime(project_id.date_start, '%Y-%m-%d') + relativedelta(days=project_id.duration or 0.0)
|
||||
result['date_end'] = newdate.strftime('%Y-%m-%d')
|
||||
return {'value': result}
|
||||
|
||||
def _check_date_start(self, cr, uid, phase, date_end, context=None):
|
||||
"""
|
||||
|
||||